YAMAÇTEPE İÇME SUYU İNŞAATI YAPTIRILACAKTIR
GAZİANTEP SU VE KANALİZASYON İDARESİ GENEL MÜDÜRLÜĞÜ
1- İdarenin a) Adresi : Değirmiçem Mah. Kıbrıs Cad. No b) Telefon ve faks numarası : 03422111300 - 3422318833 c) Elektronik posta adresi : [email protected] ç) İhale / Ön Yeterlik dokümanının görülebileceği internet adresi: www.gaski.gov.tr
2- İhale konusu yapım işinin a) Niteliği, türü ve miktarı : The Works Covered Under This Contract İs The Construction Of Yamaçtepe Drinking Water Network And Transmission Line, The Scope Of Works As Follows: • Construction Of Approximately 132 km Long Drinking Water Network And Transmission Lines Composed Of 150, 200, 250, 300, 400, 600, 800 mm Pipelines, • Construction Of 3 Water Reservoirs With 15,000 m3 Volume Each, • SCADA And Automation Work b) Yapılacağı Yer : Construction Of Yamaçtepe Drinking Water Network And Transmission Line Reference c) İşe başlama tarihi : Work Shall Commence Upon Signing Of The Contract. ç) İşin süresi : 24 Month
3- İhalenin / Ön Yeterlik / Yeterlik Değerlendirmesinin: a) Yapılacağı yer : Gaziantep Metropolitan Municipality, General Directorate Of Gaziantep Water And Wastewater Administration // Değirmiçem Mah. Kıbrıs Cd. No: 1/A Şehitkamil / 27090 Gaziantep b) Tarihi ve saati : 20.11.2026 - 14:00
4- İhaleye katılabilme şartları ve istenilen belgeler ile yeterlik değerlendirmesinde uygulanacak kriterler:
Sources Of Selection Criteria: Notice Criterion: References On Specified Works Description Of Selection Criterion: Participation As Contractor, Management Contractor, A Joint Venture Member Or Subcontractor, Within The Last Ten (10) Years (Between 1 St January 2016 And Bid Submission Deadline) İn At Least One (1) Contract, With A Value Of At Least Fifteen Million (15,000,000) Euro, Or Two (2) Contracts With A Total Value Of At Least Twenty Two Million Five Hundred Thousand (22,5 00,000) Euro. That Have Been Successfully And Substantially Completed And That Are Similar To The Proposed Works. The Similarity Shall Be Based On The Physical Size, Complexity, Methods/Technology Or Other Characteristics As Described İn Section VI, Work’s Requirements. Criterion: Average Yearly Turnover Description Of Selection Criterion: The Average Of Annual Turnovers İn Construction Works Over The Past Five (5) Financial Years (20212025) Shall Be A Minimum Of 10 Million (10,000,000) Euro Or Equivalent. Annual Turnovers Shall Be Verified By The Documents Certified By Certified (Swornin) Public Accountant Or Tax Authority. Criterion:
References On Specified Works Description Of Selection Criterion: For The Above Or Other Contracts Executed During The Period Stipulated Above, A Minimum Experience İn The Following Key Activities:
Complete Construction, İnstallation And Delivery Of A Minimum 90 km Drinking Water Transmission Main/Water Distribution Network/Wastewater Collector/Wastewater Collection Network /Stormwater Network With A Minimum Diameter Of 100 mm Under One Single Contract, Or, Complete Construction, İnstallation And Delivery Of A Minimum Total Of 135 km Drinking Water Transmission Main/Water Distribution Network/Wastewater Collector/Wastewater Collection Network/Stormwater Network With A Minimum Diameter Of 100 mm Under Two Contracts.